Construction Contracts

Understanding contract types and key clauses before signing. El-Eman Office provides transparent construction contracts across all Egyptian governorates.

Clauses that need precise wording

Disputes in any construction contract usually arise from vague clauses rather than missing ones. Points worth wording clearly include the definition of provisional and final handover and the conditions for each, how extra work is valued before it is carried out, what happens if the owner is late with payment or with providing the site, who bears the risk of material price rises during construction, and each party's right to terminate and on what terms.

Contract attachments that define the scope

Attachments must be an integral part of the contract and not a formal appendix:

  • The approved drawings, with their versions and dates.
  • Technical specifications of materials and brands, or equivalents on clear conditions.
  • A bill of quantities and item prices in unit-rate contracts.
  • The schedule and the payment stages tied to progress.
  • A list of work excluded from the contractor's scope, to avoid assumptions.

The more detailed the scope, the fewer the change orders and financial disputes.

Managing changes, payments and risk

It is best to require that any change be written and signed before execution, stating its effect on price and duration. Payment is tied to stages approved by the supervisor, and it is wise to retain part of the amount due until final handover and the correction of defects. Also confirm that insurance for workers and suitable risks is in place, and define who is liable for damage to neighbours or utilities during the works.

When choosing the contract type, a lump-sum contract suits projects with a complete design, while a unit-rate contract may suit work whose quantities will change. Cost-plus contracts require close financial control and transparent invoices.

Delay, penalties and extensions of time

Delay is among the most common causes of dispute in projects, and well-drafted wording protects both parties. The contract should state the start date clearly, how the construction period is counted, and which causes justify an extension without penalty, such as the owner's late handover of the site, late payments or late approval of drawings, or force majeure. In return, it should explain the penalty for unjustified delay and its upper limit. Any request for an extension should be written, reasoned and approved before the original period ends, not after.

Frequently asked questions

Is a verbal agreement enough for small jobs?

A written contract is always better, even for small jobs, because a written agreement fixes the scope and payments and makes it easier to prove rights in a dispute.

What happens if quantities exceed what was agreed?

It depends on the contract type. In a lump-sum contract the price may only change for work outside the scope, while in a unit-rate contract actual quantities are paid at the agreed rates.

When is the retained amount released?

According to the contract, usually after final handover, the end of the warranty period and the correction of observations.